Coral Bay Surgical Center · C-CBS-2405-06 · period ending Dec 8, 2025 · Paid

Completed to date

$128,854

Stored materials

$0

Retainage withheld

$12,885

Retainage required

$12,885

Due this application

$115,969

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$23,615$23,6152%$2,361
201-100General conditions$1,106,452$1,106,452$0$00%$0
315-400Plumbing$948,387$948,387$0$00%$0
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$0$00%$0
516-100Electrical$1,185,484$100,508$1,285,992$90,808$90,8087%$9,081
609-650Flooring and finishes$869,355$869,355$14,431$14,4312%$1,443
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$0$00%$0
Totals$9,800,000$424,938$10,224,938$0$128,854$128,854$01%$12,885

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 8Dec 11, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1Dec 14, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1Jan 19, 2026