CBS-2405 · Coral Bay Surgical Center

Everglade Electric

C-CBS-2405-06 · original $9,800,000 · retainage 10% · owner Coral Bay Health Properties Inc · lender Truist

Adjusted value

$10,224,938

Billed to date

$8,827,535 (86%)

Observed complete

90%

Amount at issue

$55,991

progress observed Aug 27, 2026 by Owner representative site walk · source site_observation_cbs-2405.pdf p.6

Draw history

AppPeriod endingStatusCompleted to dateThis periodRetainage heldRetainage requiredDue% billed
1Dec 8, 2025Paid$128,854$128,854$12,885$12,885$115,9691%
2Jan 7, 2026Paid$255,432$126,578$30,285$30,285$156,5983%
3Feb 6, 2026Paid$757,018$501,586$80,444$80,444$451,4287%
4Mar 8, 2026Paid$2,085,535$1,328,516$208,553$208,553$1,152,98720%
5Apr 7, 2026Paid$4,152,355$2,066,820$415,235$415,235$1,860,13841%
6May 7, 2026Paid$6,219,175$2,066,820$621,917$621,917$1,860,13861%
7Jun 6, 2026Paid$7,661,735$1,442,560$766,173$766,173$1,298,30475%
8Jul 6, 2026Paid$8,434,955$773,220$843,495$843,495$695,89882%
9Aug 5, 2026Certified$8,763,935$328,980$876,393$876,393$296,08286%
10Sep 4, 2026Submitted$8,827,535$63,601$882,754$882,754$57,24186%

Change orders

NumberDescriptionApplies toStatusApprovedAmount
CO-001Owner-directed revision, curtain wall and glazingline 7 — Curtain wall and glazingapprovedJan 29, 2026$202,104
CO-002Owner-directed revision, electricalline 5 — ElectricalapprovedFeb 28, 2026$100,508
CO-003Owner-directed revision, concrete, superstructureline 4 — Concrete, superstructureapprovedMar 30, 2026$122,326

Exceptions

MediumPROGRESS-REGRESSIONapplication 10$55,991

Line 3 reports $743,879 complete to date, below the $799,870 reported on the previous application

claimed $743,879supported $799,870