Drawcheck
Everglade Electric

Application 4

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Mar 8, 2026 · Paid

Completed to date

$2,085,535

Stored materials

$0

Retainage withheld

$208,553

Retainage required

$208,553

Due this application

$1,152,987

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$187,638$209,404$397,04228%$39,704
201-100General conditions$1,106,452$1,106,452$79,554$162,870$242,42422%$24,242
315-400Plumbing$948,387$948,387$11,286$139,603$150,88816%$15,089
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$0$234,963$234,9639%$23,496
516-100Electrical$1,185,484$100,508$1,285,992$227,494$174,503$401,99831%$40,200
609-650Flooring and finishes$869,355$869,355$114,668$127,969$242,63728%$24,264
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$136,378$279,205$415,58320%$41,558
Totals$9,800,000$424,938$10,224,938$757,018$1,328,516$2,085,535$020%$208,553

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 6Mar 11, 2026
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Mar 14, 2026
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Apr 19, 2026