Drawcheck
Everglade Electric

Application 5

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Apr 7, 2026 · Paid

Completed to date

$4,152,355

Stored materials

$0

Retainage withheld

$415,235

Retainage required

$415,235

Due this application

$1,860,138

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$397,042$300,022$697,06549%$69,706
201-100General conditions$1,106,452$1,106,452$242,424$233,351$475,77443%$47,577
315-400Plumbing$948,387$948,387$150,888$200,015$350,90337%$35,090
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$234,963$500,037$735,00029%$73,500
516-100Electrical$1,185,484$100,508$1,285,992$401,998$250,019$652,01651%$65,202
609-650Flooring and finishes$869,355$869,355$242,637$183,347$425,98449%$42,598
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$415,583$400,030$815,61339%$81,561
Totals$9,800,000$424,938$10,224,938$2,085,535$2,066,820$4,152,355$041%$415,235

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 12Apr 10, 2026
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Apr 13, 2026
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1May 19, 2026