Everglade Electric

Application 6

Coral Bay Surgical Center · C-CBS-2405-06 · period ending May 7, 2026 · Paid

Completed to date

$6,219,175

Stored materials

$0

Retainage withheld

$621,917

Retainage required

$621,917

Due this application

$1,860,138

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$697,065$300,022$997,08770%$99,709
201-100General conditions$1,106,452$1,106,452$475,774$233,351$709,12564%$70,912
315-400Plumbing$948,387$948,387$350,903$200,015$550,91858%$55,092
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$735,000$500,037$1,235,03750%$123,504
516-100Electrical$1,185,484$100,508$1,285,992$652,016$250,019$902,03570%$90,203
609-650Flooring and finishes$869,355$869,355$425,984$183,347$609,33170%$60,933
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$815,613$400,030$1,215,64358%$121,564
Totals$9,800,000$424,938$10,224,938$4,152,355$2,066,820$6,219,175$061%$621,917

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app06.pdf p.1 of 4May 10, 2026
conditional_waiverwaiver_cond_app06.pdf p.1 of 1May 13, 2026
unconditional_waiverwaiver_uncond_app06.pdf p.1 of 1Jun 18, 2026