Everglade Electric

Application 7

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Jun 6, 2026 · Paid

Completed to date

$7,661,735

Stored materials

$0

Retainage withheld

$766,173

Retainage required

$766,173

Due this application

$1,298,304

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$997,087$209,404$1,206,49185%$120,649
201-100General conditions$1,106,452$1,106,452$709,125$162,870$871,99579%$87,199
315-400Plumbing$948,387$948,387$550,918$139,603$690,52173%$69,052
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$1,235,037$349,006$1,584,04464%$158,404
516-100Electrical$1,185,484$100,508$1,285,992$902,035$174,503$1,076,53884%$107,654
609-650Flooring and finishes$869,355$869,355$609,331$127,969$737,30085%$73,730
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$1,215,643$279,205$1,494,84871%$149,485
Totals$9,800,000$424,938$10,224,938$6,219,175$1,442,560$7,661,735$075%$766,173

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app07.pdf p.1 of 10Jun 9, 2026
conditional_waiverwaiver_cond_app07.pdf p.1 of 1Jun 12, 2026
unconditional_waiverwaiver_uncond_app07.pdf p.1 of 1Jul 18, 2026