Application 8

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Jul 6, 2026 · Paid

Completed to date

$8,434,955

Stored materials

$0

Retainage withheld

$843,495

Retainage required

$843,495

Due this application

$695,898

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581—$1,422,581$1,206,491$112,242$1,318,732—93%$131,873
201-100General conditions$1,106,452—$1,106,452$871,995$87,299$959,294—87%$95,929
315-400Plumbing$948,387—$948,387$690,521$74,828$765,348—81%$76,535
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$1,584,044$187,069$1,771,113—71%$177,111
516-100Electrical$1,185,484$100,508$1,285,992$1,076,538$93,535$1,170,073—91%$117,007
609-650Flooring and finishes$869,355—$869,355$737,300$68,592$805,892—93%$80,589
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$1,494,848$149,655$1,644,503—78%$164,450
Totals$9,800,000$424,938$10,224,938$7,661,735$773,220$8,434,955$082%$843,495

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app08.pdf p.1 of 11—Jul 9, 2026
conditional_waiverwaiver_cond_app08.pdf p.1 of 1—Jul 12, 2026
unconditional_waiverwaiver_uncond_app08.pdf p.1 of 1—Aug 17, 2026