Drawcheck
Everglade Electric

Application 9

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Aug 5, 2026 · Certified

Completed to date

$8,763,935

Stored materials

$0

Retainage withheld

$876,393

Retainage required

$876,393

Due this application

$296,082

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$1,318,732$51,782$1,370,51496%$137,051
201-100General conditions$1,106,452$1,106,452$959,294$40,275$999,56890%$99,957
315-400Plumbing$948,387$948,387$765,348$34,521$799,87084%$79,987
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$1,771,113$86,303$1,857,41675%$185,742
516-100Electrical$1,185,484$100,508$1,285,992$1,170,073$15,411$1,185,48492%$118,548
609-650Flooring and finishes$869,355$869,355$805,892$31,645$837,53696%$83,754
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$1,644,503$69,043$1,713,54682%$171,355
Totals$9,800,000$424,938$10,224,938$8,434,955$328,980$8,763,935$086%$876,393

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app09.pdf p.1 of 5Aug 8, 2026
conditional_waiverwaiver_cond_app09.pdf p.1 of 1Aug 11, 2026