Drawcheck
Everglade Electric

Application 10

Coral Bay Surgical Center · C-CBS-2405-06 · period ending Sep 4, 2026 · Submitted

Completed to date

$8,827,535

Stored materials

$0

Retainage withheld

$882,754

Retainage required

$882,754

Due this application

$57,241

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
103-300Concrete, foundations$1,422,581$1,422,581$1,370,514$22,192$1,392,70698%$139,271
201-100General conditions$1,106,452$1,106,452$999,568$17,261$1,016,82992%$101,683
315-400Plumbing$948,387$948,387$799,870-$55,991$743,87978%$74,388
403-330Concrete, superstructure$2,370,968$122,326$2,493,293$1,857,416$36,987$1,894,40376%$189,440
516-100Electrical$1,185,484$100,508$1,285,992$1,185,484$0$1,185,48492%$118,548
609-650Flooring and finishes$869,355$869,355$837,536$13,562$851,09898%$85,110
708-400Curtain wall and glazing$1,896,774$202,104$2,098,878$1,713,546$29,590$1,743,13583%$174,314
Totals$9,800,000$424,938$10,224,938$8,763,935$63,601$8,827,535$086%$882,754

Exceptions on this application

MediumPROGRESS-REGRESSIONCumulative completed work went backwards$55,991

Line 3 reports $743,879 complete to date, below the $799,870 reported on the previous application

A cumulative figure that falls means an earlier application overstated progress, or the schedule of values has been quietly re-cut between draws. Either one changes what was already paid.

Remedy Require a written reconciliation of the prior application before certifying this one.

claimed $743,879supported $799,870continuation line 3 (15-400)

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app10.pdf p.1 of 4Sep 7, 2026
conditional_waiverwaiver_cond_app10.pdf p.1 of 1Sep 10, 2026