Aventura Logistics Park · C-AVL-2312-07 · period ending Aug 20, 2025 · Paid

Completed to date

$574,032

Stored materials

$0

Retainage withheld

$28,702

Retainage required

$28,702

Due this application

$545,331

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000—$2,961,000—$34,644$34,644—1%$1,732
202-200Sitework and excavation$2,326,500$225,371$2,551,871—$0$0—0%$0
303-300Concrete, foundations$3,807,000$237,240$4,044,240—$0$0—0%$0
403-330Concrete, superstructure$6,345,000—$6,345,000—$0$0—0%$0
505-100Structural steel$4,018,500—$4,018,500—$288,126$288,126—7%$14,406
607-500Roofing and waterproofing$1,903,500—$1,903,500—$22,271$22,271—1%$1,114
708-400Curtain wall and glazing$5,076,000—$5,076,000—$0$0—0%$0
809-250Drywall and framing$2,961,000—$2,961,000—$0$0—0%$0
909-650Flooring and finishes$2,326,500—$2,326,500—$0$0—0%$0
1015-400Plumbing$2,538,000$260,158$2,798,158—$181,975$181,975—7%$9,099
1115-700HVAC$4,018,500—$4,018,500—$47,016$47,016—1%$2,351
1216-100Electrical$3,172,500—$3,172,500—$0$0—0%$0
1321-100Fire protection$846,000—$846,000—$0$0—0%$0
Totals$42,300,000$722,768$43,022,768$0$574,032$574,032$01%$28,702

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app01.pdf p.1 of 11—Aug 23, 2025
conditional_waiverwaiver_cond_app01.pdf p.1 of 1—Aug 26, 2025
unconditional_waiverwaiver_uncond_app01.pdf p.1 of 1—Oct 1, 2025