Drawcheck
Keystone Contracting

Application 2

Aventura Logistics Park · C-AVL-2312-07 · period ending Sep 19, 2025 · Paid

Completed to date

$895,174

Stored materials

$160,740

Retainage withheld

$52,796

Retainage required

$52,796

Due this application

$457,788

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$34,644$61,589$96,2333%$4,812
202-200Sitework and excavation$2,326,500$225,371$2,551,871$0$0$00%$0
303-300Concrete, foundations$3,807,000$237,240$4,044,240$0$0$00%$0
403-330Concrete, superstructure$6,345,000$6,345,000$0$0$00%$0
505-100Structural steel$4,018,500$4,018,500$288,126$83,585$371,711$160,7409%$26,623
607-500Roofing and waterproofing$1,903,500$1,903,500$22,271$39,593$61,8643%$3,093
708-400Curtain wall and glazing$5,076,000$5,076,000$0$0$00%$0
809-250Drywall and framing$2,961,000$2,961,000$0$0$00%$0
909-650Flooring and finishes$2,326,500$2,326,500$0$0$00%$0
1015-400Plumbing$2,538,000$260,158$2,798,158$181,975$52,790$234,7658%$11,738
1115-700HVAC$4,018,500$4,018,500$47,016$83,585$130,6013%$6,530
1216-100Electrical$3,172,500$3,172,500$0$0$00%$0
1321-100Fire protection$846,000$846,000$0$0$00%$0
Totals$42,300,000$722,768$43,022,768$574,032$321,142$895,174$160,7402%$52,796

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app02.pdf p.1 of 7Sep 22, 2025
conditional_waiverwaiver_cond_app02.pdf p.1 of 1Sep 25, 2025
supplier_invoiceinvoice_glazing_4471.pdf p.1 of 3$88,830Sep 23, 2025
unconditional_waiverwaiver_uncond_app02.pdf p.1 of 1Oct 31, 2025