Drawcheck
Keystone Contracting

Application 3

Aventura Logistics Park · C-AVL-2312-07 · period ending Oct 19, 2025 · Paid

Completed to date

$1,616,325

Stored materials

$160,740

Retainage withheld

$88,853

Retainage required

$88,853

Due this application

$685,094

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$96,233$115,183$211,4157%$10,571
202-200Sitework and excavation$2,326,500$225,371$2,551,871$0$26,522$26,5221%$1,326
303-300Concrete, foundations$3,807,000$237,240$4,044,240$0$0$00%$0
403-330Concrete, superstructure$6,345,000$6,345,000$0$0$00%$0
505-100Structural steel$4,018,500$4,018,500$371,711$156,320$528,031$160,74013%$34,439
607-500Roofing and waterproofing$1,903,500$1,903,500$61,864$74,046$135,9107%$6,795
708-400Curtain wall and glazing$5,076,000$5,076,000$0$57,866$57,8661%$2,893
809-250Drywall and framing$2,961,000$2,961,000$0$0$00%$0
909-650Flooring and finishes$2,326,500$2,326,500$0$0$00%$0
1015-400Plumbing$2,538,000$260,158$2,798,158$234,765$98,728$333,49312%$16,675
1115-700HVAC$4,018,500$4,018,500$130,601$156,320$286,9217%$14,346
1216-100Electrical$3,172,500$3,172,500$0$36,167$36,1671%$1,808
1321-100Fire protection$846,000$846,000$0$0$00%$0
Totals$42,300,000$722,768$43,022,768$895,174$721,152$1,616,325$160,7404%$88,853

Exceptions on this application

CriticalINVOICE-REUSEDSupplier invoice supporting two applications$88,830

Supplier invoice invoice_glazing_4471.pdf appears on applications 2 and 3 for the same amount

The same invoice appears as backup on two draws for the same amount. Either the material was billed twice or the backup is wrong, and both need answering before payment.

Remedy Withhold the duplicated amount and require the contractor to identify which application the invoice supports.

claimed invoice_glazing_4471.pdfsupported one applicationcontinuation line 5 (05-100)

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app03.pdf p.1 of 5Oct 22, 2025
conditional_waiverwaiver_cond_app03.pdf p.1 of 1Oct 25, 2025
supplier_invoiceinvoice_glazing_4471.pdf p.1 of 1$88,830Oct 23, 2025
unconditional_waiverwaiver_uncond_app03.pdf p.1 of 1Nov 30, 2025