Application 4

Aventura Logistics Park · C-AVL-2312-07 · period ending Nov 18, 2025 · Paid

Completed to date

$3,570,014

Stored materials

$0

Retainage withheld

$178,501

Retainage required

$178,501

Due this application

$1,703,302

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$211,415$204,605$416,02114%$20,801
202-200Sitework and excavation$2,326,500$225,371$2,551,871$26,522$160,761$187,2837%$9,364
303-300Concrete, foundations$3,807,000$237,240$4,044,240$0$78,044$78,0442%$3,902
403-330Concrete, superstructure$6,345,000$6,345,000$0$0$00%$0
505-100Structural steel$4,018,500$4,018,500$528,031$277,678$805,70920%$40,285
607-500Roofing and waterproofing$1,903,500$1,903,500$135,910$131,532$267,44214%$13,372
708-400Curtain wall and glazing$5,076,000$5,076,000$57,866$350,752$408,6188%$20,431
809-250Drywall and framing$2,961,000$2,961,000$0$60,701$60,7012%$3,035
909-650Flooring and finishes$2,326,500$2,326,500$0$0$00%$0
1015-400Plumbing$2,538,000$260,158$2,798,158$333,493$175,376$508,86918%$25,443
1115-700HVAC$4,018,500$4,018,500$286,921$277,678$564,59914%$28,230
1216-100Electrical$3,172,500$3,172,500$36,167$219,220$255,3868%$12,769
1321-100Fire protection$846,000$846,000$0$17,343$17,3432%$867
Totals$42,300,000$722,768$43,022,768$1,616,325$1,953,689$3,570,014$08%$178,501

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app04.pdf p.1 of 12Nov 21, 2025
conditional_waiverwaiver_cond_app04.pdf p.1 of 1Nov 24, 2025
unconditional_waiverwaiver_uncond_app04.pdf p.1 of 1Dec 30, 2025