Application 5

Aventura Logistics Park · C-AVL-2312-07 · period ending Dec 18, 2025 · Paid

Completed to date

$7,918,560

Stored materials

$0

Retainage withheld

$395,928

Retainage required

$395,928

Due this application

$4,131,118

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$416,021$328,375$744,39525%$37,220
202-200Sitework and excavation$2,326,500$225,371$2,551,871$187,283$258,009$445,29217%$22,265
303-300Concrete, foundations$3,807,000$237,240$4,044,240$78,044$422,196$500,24012%$25,012
403-330Concrete, superstructure$6,345,000$6,345,000$0$453,033$453,0337%$22,652
505-100Structural steel$4,018,500$4,018,500$805,709$445,652$1,251,36131%$62,568
607-500Roofing and waterproofing$1,903,500$1,903,500$267,442$211,098$478,54025%$23,927
708-400Curtain wall and glazing$5,076,000$5,076,000$408,618$562,928$971,54619%$48,577
809-250Drywall and framing$2,961,000$2,961,000$60,701$328,375$389,07513%$19,454
909-650Flooring and finishes$2,326,500$2,326,500$0$166,112$166,1127%$8,306
1015-400Plumbing$2,538,000$260,158$2,798,158$508,869$281,464$790,33328%$39,517
1115-700HVAC$4,018,500$4,018,500$564,599$445,652$1,010,25125%$50,513
1216-100Electrical$3,172,500$3,172,500$255,386$351,830$607,21719%$30,361
1321-100Fire protection$846,000$846,000$17,343$93,821$111,16413%$5,558
Totals$42,300,000$722,768$43,022,768$3,570,014$4,348,546$7,918,560$018%$395,928

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app05.pdf p.1 of 4Dec 21, 2025
conditional_waiverwaiver_cond_app05.pdf p.1 of 1Dec 24, 2025
unconditional_waiverwaiver_uncond_app05.pdf p.1 of 1Jan 29, 2026