Aventura Logistics Park · C-AVL-2312-07 · period ending Jan 17, 2026 · Paid

Completed to date

$14,386,230

Stored materials

$0

Retainage withheld

$719,312

Retainage required

$719,312

Due this application

$6,144,286

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$744,395$452,737$1,197,13240%$59,857
202-200Sitework and excavation$2,326,500$225,371$2,551,871$445,292$355,722$801,01431%$40,051
303-300Concrete, foundations$3,807,000$237,240$4,044,240$500,240$582,090$1,082,33027%$54,117
403-330Concrete, superstructure$6,345,000$6,345,000$453,033$970,151$1,423,18422%$71,159
505-100Structural steel$4,018,500$4,018,500$1,251,361$614,429$1,865,79046%$93,289
607-500Roofing and waterproofing$1,903,500$1,903,500$478,540$291,045$769,58540%$38,479
708-400Curtain wall and glazing$5,076,000$5,076,000$971,546$776,120$1,747,66734%$87,383
809-250Drywall and framing$2,961,000$2,961,000$389,075$452,737$841,81228%$42,091
909-650Flooring and finishes$2,326,500$2,326,500$166,112$355,722$521,83422%$26,092
1015-400Plumbing$2,538,000$260,158$2,798,158$790,333$388,060$1,178,39342%$58,920
1115-700HVAC$4,018,500$4,018,500$1,010,251$614,429$1,624,68040%$81,234
1216-100Electrical$3,172,500$3,172,500$607,217$485,075$1,092,29234%$54,615
1321-100Fire protection$846,000$846,000$111,164$129,353$240,51828%$12,026
Totals$42,300,000$722,768$43,022,768$7,918,560$6,467,670$14,386,230$033%$719,312

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app06.pdf p.1 of 13Jan 20, 2026
conditional_waiverwaiver_cond_app06.pdf p.1 of 1Jan 23, 2026
unconditional_waiverwaiver_uncond_app06.pdf p.1 of 1Feb 28, 2026