Drawcheck
Keystone Contracting

Application 7

Aventura Logistics Park · C-AVL-2312-07 · period ending Feb 16, 2026 · Paid

Completed to date

$21,636,450

Stored materials

$0

Retainage withheld

$1,081,822

Retainage required

$1,081,823

Due this application

$6,887,709

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$2,961,000$2,961,000$1,197,132$507,515$1,704,64858%$85,232
202-200Sitework and excavation$2,326,500$225,371$2,551,871$801,014$398,762$1,199,77647%$59,989
303-300Concrete, foundations$3,807,000$237,240$4,044,240$1,082,330$652,520$1,734,85043%$86,742
403-330Concrete, superstructure$6,345,000$6,345,000$1,423,184$1,087,533$2,510,71740%$125,536
505-100Structural steel$4,018,500$4,018,500$1,865,790$688,771$2,554,56064%$127,728
607-500Roofing and waterproofing$1,903,500$1,903,500$769,585$326,260$1,095,84558%$54,792
708-400Curtain wall and glazing$5,076,000$5,076,000$1,747,667$870,026$2,617,69352%$130,885
809-250Drywall and framing$2,961,000$2,961,000$841,812$507,515$1,349,32846%$67,466
909-650Flooring and finishes$2,326,500$2,326,500$521,834$398,762$920,59640%$46,030
1015-400Plumbing$2,538,000$260,158$2,798,158$1,178,393$435,013$1,613,40758%$80,670
1115-700HVAC$4,018,500$4,018,500$1,624,680$688,771$2,313,45058%$115,673
1216-100Electrical$3,172,500$3,172,500$1,092,292$543,767$1,636,05852%$81,803
1321-100Fire protection$846,000$846,000$240,518$145,004$385,52246%$19,276
Totals$42,300,000$722,768$43,022,768$14,386,230$7,250,220$21,636,450$050%$1,081,822

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app07.pdf p.1 of 7Feb 19, 2026
conditional_waiverwaiver_cond_app07.pdf p.1 of 1Feb 22, 2026
unconditional_waiverwaiver_uncond_app07.pdf p.1 of 1Mar 30, 2026