Brickell Bay Tower · C-BRK-2201-01 · period ending Nov 28, 2025 · Paid

Completed to date

$96,486,041

Stored materials

$0

Retainage withheld

$9,648,604

Retainage required

$9,648,604

Due this application

$23,221,708

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000—$10,395,000$7,895,003$2,499,998$10,395,000—100%$1,039,500
202-200Sitework and excavation$8,167,500—$8,167,500$5,443,639$1,967,306$7,410,944—91%$741,094
303-300Concrete, foundations$13,365,000—$13,365,000$7,664,828$3,219,228$10,884,055—81%$1,088,406
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$6,905,250$3,461,535$10,366,785—43%$1,036,679
505-100Structural steel$14,107,500—$14,107,500$7,759,125$2,192,306$9,951,431—71%$995,143
607-500Roofing and waterproofing$6,682,500—$6,682,500$3,274,425$1,038,461$4,312,886—65%$431,289
708-400Curtain wall and glazing$17,820,000—$17,820,000$7,662,600$2,769,228$10,431,828—59%$1,043,183
809-250Drywall and framing$10,395,000—$10,395,000$3,846,150$1,615,383$5,461,533—53%$546,153
909-650Flooring and finishes$8,167,500—$8,167,500$2,531,925$1,269,230$3,801,155—47%$380,115
1015-400Plumbing$8,910,000$830,266$9,740,266$4,900,500$1,384,614$6,285,114—65%$628,511
1115-700HVAC$14,107,500$662,148$14,769,648$6,912,675$2,192,306$9,104,981—62%$910,498
1216-100Electrical$11,137,500—$11,137,500$4,789,125$1,730,768$6,519,893—59%$651,989
1321-100Fire protection$2,970,000—$2,970,000$1,098,900$461,538$1,560,438—53%$156,044
Totals$148,500,000$3,197,001$151,697,001$70,684,144$25,801,897$96,486,041$064%$9,648,604

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app08.pdf p.1 of 8—Dec 1, 2025
conditional_waiverwaiver_cond_app08.pdf p.1 of 1—Dec 4, 2025
unconditional_waiverwaiver_uncond_app08.pdf p.1 of 1—Jan 9, 2026