Application 8
Aventura Logistics Park · C-AVL-2312-07 · period ending Mar 18, 2026 · PaidCompleted to date
$28,104,120
Stored materials
$0
Retainage withheld
$1,405,206
Retainage required
$1,405,206
Due this application
$6,144,286
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $2,961,000 | — | $2,961,000 | $1,704,648 | $452,737 | $2,157,385 | — | 73% | $107,869 |
| 2 | 02-200 | Sitework and excavation | $2,326,500 | $225,371 | $2,551,871 | $1,199,776 | $355,722 | $1,555,498 | — | 61% | $77,775 |
| 3 | 03-300 | Concrete, foundations | $3,807,000 | $237,240 | $4,044,240 | $1,734,850 | $582,090 | $2,316,940 | — | 57% | $115,847 |
| 4 | 03-330 | Concrete, superstructure | $6,345,000 | — | $6,345,000 | $2,510,717 | $970,151 | $3,480,867 | — | 55% | $174,043 |
| 5 | 05-100 | Structural steel | $4,018,500 | — | $4,018,500 | $2,554,560 | $614,429 | $3,168,989 | — | 79% | $158,449 |
| 6 | 07-500 | Roofing and waterproofing | $1,903,500 | — | $1,903,500 | $1,095,845 | $291,045 | $1,386,890 | — | 73% | $69,345 |
| 7 | 08-400 | Curtain wall and glazing | $5,076,000 | — | $5,076,000 | $2,617,693 | $776,120 | $3,393,814 | — | 67% | $169,691 |
| 8 | 09-250 | Drywall and framing | $2,961,000 | — | $2,961,000 | $1,349,328 | $452,737 | $1,802,065 | — | 61% | $90,103 |
| 9 | 09-650 | Flooring and finishes | $2,326,500 | — | $2,326,500 | $920,596 | $355,722 | $1,276,318 | — | 55% | $63,816 |
| 10 | 15-400 | Plumbing | $2,538,000 | $260,158 | $2,798,158 | $1,613,407 | $388,060 | $2,001,467 | — | 72% | $100,073 |
| 11 | 15-700 | HVAC | $4,018,500 | — | $4,018,500 | $2,313,450 | $614,429 | $2,927,879 | — | 73% | $146,394 |
| 12 | 16-100 | Electrical | $3,172,500 | — | $3,172,500 | $1,636,058 | $485,075 | $2,121,134 | — | 67% | $106,057 |
| 13 | 21-100 | Fire protection | $846,000 | — | $846,000 | $385,522 | $129,353 | $514,876 | — | 61% | $25,744 |
| Totals | $42,300,000 | $722,768 | $43,022,768 | $21,636,450 | $6,467,670 | $28,104,120 | $0 | 65% | $1,405,206 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app08.pdf p.1 of 14 | — | Mar 21, 2026 |
| conditional_waiver | waiver_cond_app08.pdf p.1 of 1 | — | Mar 24, 2026 |
| unconditional_waiver | waiver_uncond_app08.pdf p.1 of 1 | — | Apr 29, 2026 |