← Keystone Contracting
Application 10
Aventura Logistics Park · C-AVL-2312-07 · period ending May 17, 2026 · PaidCompleted to date
$35,718,120
Stored materials
$0
Retainage withheld
$1,785,906
Retainage required
$1,785,906
Due this application
$2,776,784
Continuation sheet
Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.
| # | Cost code | Description | Base value | Approved COs | Adjusted value | Previous | This period | Completed to date | Stored | % | Retainage |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 01-100 | General conditions | $2,961,000 | — | $2,961,000 | $2,485,760 | $204,605 | $2,690,365 | — | 91% | $134,518 |
| 2 | 02-200 | Sitework and excavation | $2,326,500 | $225,371 | $2,551,871 | $1,813,507 | $160,761 | $1,974,268 | — | 77% | $98,713 |
| 3 | 03-300 | Concrete, foundations | $3,807,000 | $237,240 | $4,044,240 | $2,739,137 | $263,064 | $3,002,200 | — | 74% | $150,110 |
| 4 | 03-330 | Concrete, superstructure | $6,345,000 | — | $6,345,000 | $4,184,528 | $438,440 | $4,622,967 | — | 73% | $231,148 |
| 5 | 05-100 | Structural steel | $4,018,500 | — | $4,018,500 | $3,614,641 | $277,678 | $3,892,319 | — | 97% | $194,616 |
| 6 | 07-500 | Roofing and waterproofing | $1,903,500 | — | $1,903,500 | $1,597,988 | $131,532 | $1,729,520 | — | 91% | $86,476 |
| 7 | 08-400 | Curtain wall and glazing | $5,076,000 | — | $5,076,000 | $3,956,742 | $350,752 | $4,307,494 | — | 85% | $215,375 |
| 8 | 09-250 | Drywall and framing | $2,961,000 | — | $2,961,000 | $2,130,440 | $204,605 | $2,335,045 | — | 79% | $116,752 |
| 9 | 09-650 | Flooring and finishes | $2,326,500 | — | $2,326,500 | $1,534,327 | $160,761 | $1,695,088 | — | 73% | $84,754 |
| 10 | 15-400 | Plumbing | $2,538,000 | $260,158 | $2,798,158 | $2,282,931 | $175,376 | $2,458,307 | — | 88% | $122,915 |
| 11 | 15-700 | HVAC | $4,018,500 | — | $4,018,500 | $3,373,531 | $277,678 | $3,651,209 | — | 91% | $182,560 |
| 12 | 16-100 | Electrical | $3,172,500 | — | $3,172,500 | $2,472,964 | $219,220 | $2,692,184 | — | 85% | $134,609 |
| 13 | 21-100 | Fire protection | $846,000 | — | $846,000 | $608,697 | $58,459 | $667,156 | — | 79% | $33,358 |
| Totals | $42,300,000 | $722,768 | $43,022,768 | $32,795,190 | $2,922,930 | $35,718,120 | $0 | 83% | $1,785,906 | ||
Exceptions on this application
Every rule passes on this application.
Documents submitted with the draw
| Kind | File | Amount | Received |
|---|---|---|---|
| certified_payroll | payroll_app10.pdf p.1 of 10 | — | May 20, 2026 |
| conditional_waiver | waiver_cond_app10.pdf p.1 of 1 | — | May 23, 2026 |
| unconditional_waiver | waiver_uncond_app10.pdf p.1 of 1 | — | Jun 28, 2026 |