Brickell Bay Tower · C-BRK-2201-01 · period ending Dec 28, 2025 · Paid

Completed to date

$114,644,822

Stored materials

$0

Retainage withheld

$11,464,482

Retainage required

$11,464,482

Due this application

$16,342,902

Continuation sheet

Scheduled value is shown adjusted for approved change orders only. Rows shaded red carry an exception; the reason is listed beneath the table.

#Cost codeDescriptionBase valueApproved COsAdjusted valuePreviousThis periodCompleted to dateStored%Retainage
101-100General conditions$10,395,000—$10,395,000$10,395,000$0$10,395,000—100%$1,039,500
202-200Sitework and excavation$8,167,500—$8,167,500$7,410,944$756,556$8,167,500—100%$816,750
303-300Concrete, foundations$13,365,000—$13,365,000$10,884,055$2,480,945$13,365,000—100%$1,336,500
403-330Concrete, superstructure$22,275,000$1,704,586$23,979,586$10,366,785$2,851,200$13,217,985—55%$1,321,799
505-100Structural steel$14,107,500—$14,107,500$9,951,431$1,805,760$11,757,191—83%$1,175,719
607-500Roofing and waterproofing$6,682,500—$6,682,500$4,312,886$855,360$5,168,246—77%$516,825
708-400Curtain wall and glazing$17,820,000—$17,820,000$10,431,828$2,280,960$12,712,788—71%$1,271,279
809-250Drywall and framing$10,395,000—$10,395,000$5,461,533$1,330,560$6,792,093—65%$679,209
909-650Flooring and finishes$8,167,500—$8,167,500$3,801,155$1,045,440$4,846,595—59%$484,659
1015-400Plumbing$8,910,000$830,266$9,740,266$6,285,114$1,140,480$7,425,594—76%$742,559
1115-700HVAC$14,107,500$662,148$14,769,648$9,104,981$1,805,760$10,910,741—74%$1,091,074
1216-100Electrical$11,137,500—$11,137,500$6,519,893$1,425,600$7,945,493—71%$794,549
1321-100Fire protection$2,970,000—$2,970,000$1,560,438$380,160$1,940,598—65%$194,060
Totals$148,500,000$3,197,001$151,697,001$96,486,041$18,158,780$114,644,822$076%$11,464,482

Exceptions on this application

Every rule passes on this application.

Documents submitted with the draw

KindFileAmountReceived
certified_payrollpayroll_app09.pdf p.1 of 5—Dec 31, 2025
conditional_waiverwaiver_cond_app09.pdf p.1 of 1—Jan 3, 2026
unconditional_waiverwaiver_uncond_app09.pdf p.1 of 1—Feb 8, 2026