1 exceptions, $246,120 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

CriticalCO-UNAPPROVED-BILLEDMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 is billed $246,120 above its base value while change orders totalling $215,694 on this line are still unapproved

Why it matters Paying against a pending change order concedes the change order. The owner loses the ability to negotiate the price after the work has been paid for.

claimed $4,348,120supported $4,102,000application 10C-CBS-2405-05