1 exceptions, $55,991 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

MediumPROGRESS-REGRESSIONEverglade ElectricCoral Bay Surgical Center$55,991

Line 3 reports $743,879 complete to date, below the $799,870 reported on the previous application

Why it matters A cumulative figure that falls means an earlier application overstated progress, or the schedule of values has been quietly re-cut between draws. Either one changes what was already paid.

claimed $743,879supported $799,870application 10C-CBS-2405-06