CriticalBILLING-AHEAD-OF-PROGRESSVantage Construction GroupBrickell Bay Tower$21,298,259
Application 14 bills 90.8 percent of the adjusted contract against an observed 76.7 percent complete on Aug 27 2026
Why it matters Front loading moves the contractor's risk onto the owner. If the contractor leaves the job, the remaining money will not buy the remaining work, and that gap is only visible before it is paid.