Drawcheck

Exception ledger

3 exceptions, $733,173 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

CriticalOVERBILL-LINECordova Glass SystemsBrickell Bay Tower$431,063

Line 2 (Structural steel) is billed to $5,220,646 against an adjusted scheduled value of $4,789,583

Why it matters A schedule-of-values line cannot be worth more than its scheduled value plus the approved change orders against it. Anything above that is money claimed for scope that has not been priced or approved.

claimed $5,220,646supported $4,789,583application 14C-BRK-2201-02
CriticalOVERBILL-LINEMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 (General conditions) is billed to $4,348,120 against an adjusted scheduled value of $4,102,000

Why it matters A schedule-of-values line cannot be worth more than its scheduled value plus the approved change orders against it. Anything above that is money claimed for scope that has not been priced or approved.

claimed $4,348,120supported $4,102,000application 10C-CBS-2405-05
MediumPROGRESS-REGRESSIONEverglade ElectricCoral Bay Surgical Center$55,991

Line 3 reports $743,879 complete to date, below the $799,870 reported on the previous application

Why it matters A cumulative figure that falls means an earlier application overstated progress, or the schedule of values has been quietly re-cut between draws. Either one changes what was already paid.

claimed $743,879supported $799,870application 10C-CBS-2405-06