Drawcheck

Exception ledger

1 exceptions, $5,233,149 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

HighRETAINAGE-SHORTVantage Construction GroupBrickell Bay Tower$5,233,149

Retainage withheld on application 14 is $8,538,296 against $13,771,445 required at 10.0 percent

Why it matters Retainage is the owner's only remaining leverage at closeout. Under-withholding gives it away quietly, one draw at a time, and it is almost never noticed until the punch list stalls.

claimed $8,538,296supported $13,771,445application 14C-BRK-2201-01