Exception ledger

3 exceptions, $259,917 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

HighSTORED-NO-INVOICECordova Glass SystemsBrickell Bay Tower$110,917

$110,917 of stored materials claimed on line 5 with no supplier invoice or bill of sale in the application

Why it matters Stored materials are paid for before they are installed, so the only protection is proof the material exists, is paid for, and is titled to the project.

claimed $110,917supported supporting invoice requiredapplication 3C-BRK-2201-02
HighSTORED-NOT-PERMITTEDDelmar MechanicalWynwood Yards Mixed Use$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

Why it matters The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

claimed $74,500supported not permittedapplication 2C-WYN-2304-04
HighSTORED-NOT-PERMITTEDDelmar MechanicalWynwood Yards Mixed Use$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

Why it matters The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

claimed $74,500supported not permittedapplication 3C-WYN-2304-04