5 exceptions, $22,310,391 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

CriticalBILLING-AHEAD-OF-PROGRESSVantage Construction GroupBrickell Bay Tower$21,298,259

Application 14 bills 90.8 percent of the adjusted contract against an observed 76.7 percent complete on Aug 27 2026

Why it matters Front loading moves the contractor's risk onto the owner. If the contractor leaves the job, the remaining money will not buy the remaining work, and that gap is only visible before it is paid.

claimed 90.8%supported 76.7%application 14C-BRK-2201-01
CriticalOVERBILL-LINECordova Glass SystemsBrickell Bay Tower$431,063

Line 2 (Structural steel) is billed to $5,220,646 against an adjusted scheduled value of $4,789,583

Why it matters A schedule-of-values line cannot be worth more than its scheduled value plus the approved change orders against it. Anything above that is money claimed for scope that has not been priced or approved.

claimed $5,220,646supported $4,789,583application 14C-BRK-2201-02
CriticalOVERBILL-LINEMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 (General conditions) is billed to $4,348,120 against an adjusted scheduled value of $4,102,000

Why it matters A schedule-of-values line cannot be worth more than its scheduled value plus the approved change orders against it. Anything above that is money claimed for scope that has not been priced or approved.

claimed $4,348,120supported $4,102,000application 10C-CBS-2405-05
CriticalCO-UNAPPROVED-BILLEDMeridian BuildersCoral Bay Surgical Center$246,120

Line 1 is billed $246,120 above its base value while change orders totalling $215,694 on this line are still unapproved

Why it matters Paying against a pending change order concedes the change order. The owner loses the ability to negotiate the price after the work has been paid for.

claimed $4,348,120supported $4,102,000application 10C-CBS-2405-05
CriticalINVOICE-REUSEDKeystone ContractingAventura Logistics Park$88,830

Supplier invoice invoice_glazing_4471.pdf appears on applications 2 and 3 for the same amount

Why it matters The same invoice appears as backup on two draws for the same amount. Either the material was billed twice or the backup is wrong, and both need answering before payment.

claimed invoice_glazing_4471.pdfsupported one applicationapplication 3C-AVL-2312-07