5 exceptions, $8,545,223 at issue

Each row states what was claimed, what the contract and the supporting documents actually support, and the difference between them.

HighRETAINAGE-SHORTVantage Construction GroupBrickell Bay Tower$5,233,149

Retainage withheld on application 14 is $8,538,296 against $13,771,445 required at 10.0 percent

Why it matters Retainage is the owner's only remaining leverage at closeout. Under-withholding gives it away quietly, one draw at a time, and it is almost never noticed until the punch list stalls.

claimed $8,538,296supported $13,771,445application 14C-BRK-2201-01
HighWAIVER-MISSINGMeridian BuildersWynwood Yards Mixed Use$3,052,157

Application 10 was paid on Jul 26 2026 and no unconditional lien waiver has been received for it

Why it matters Payment without an unconditional waiver leaves the owner exposed to a lien for work already paid for. It is the single most common way an owner pays twice.

claimed no waiver on filesupported unconditional waiver requiredapplication 10C-WYN-2304-03
HighSTORED-NO-INVOICECordova Glass SystemsBrickell Bay Tower$110,917

$110,917 of stored materials claimed on line 5 with no supplier invoice or bill of sale in the application

Why it matters Stored materials are paid for before they are installed, so the only protection is proof the material exists, is paid for, and is titled to the project.

claimed $110,917supported supporting invoice requiredapplication 3C-BRK-2201-02
HighSTORED-NOT-PERMITTEDDelmar MechanicalWynwood Yards Mixed Use$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

Why it matters The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

claimed $74,500supported not permittedapplication 2C-WYN-2304-04
HighSTORED-NOT-PERMITTEDDelmar MechanicalWynwood Yards Mixed Use$74,500

$74,500 of stored materials claimed on line 5 under a contract that does not permit billing for stored materials

Why it matters The contract does not permit billing for materials before installation. Paying anyway waives a term the owner negotiated.

claimed $74,500supported not permittedapplication 3C-WYN-2304-04